Which of the following is the most reliable estimate?
-
A.
Detailed estimate
-
B.
Plinth area estimate
-
C.
Cube rate estimate
-
D.
Preliminary estimate
Correct Answer:
A. Detailed estimate
Explanation:
A detailed estimate is considered the most reliable because it involves a comprehensive and systematic analysis of all project components. Unlike preliminary or area-based estimates that rely on broad historical averages, a detailed estimate utilizes complete architectural drawings and technical specifications to perform a precise quantity takeoff. By itemizing specific costs for materials, labor, equipment, and overhead, it provides the most accurate financial projection, typically achieving an accuracy range of ±5% to ±10% at the final design stage.