Engineering Exams RRB-JE Civil and Allied Engineering Technical Abilities 2019 19-Sept-2019 Paper-2 Shift-1 Medium +1 -0.33
The purpose of a Well Point System is -
Correct Answer: B. Dewatering
Explanation: A Well Point System is a widely used method for dewatering excavation sites by lowering the groundwater level. It consists of a series of small-diameter pipes driven into the ground, connected to a header pipe and a vacuum pump. By continuously extracting water from the soil, it creates a dry and stable working environment, preventing soil instability or flooding during construction activities.