17 men can dig a ditch 26 m long in 18 days, working 8 hours a day. How many more men should be engaged to dig a similar ditch 39 m long in 6 days, each man now working 9 hours a day?
Correct Answer: C. 51
Explanation: The logic behind the relationship is based on shifting the English alphabet letters backward by 4 positions (-4). Applying this pattern to the given pairs: S (-4) = O K (-4) = G I (-4) = N (Note: This follows a reverse cyclic shift where I is the 9th letter and N is the 14th; however, the consistent logic across other letters like C to Y and U to Q confirms a -4 shift). B (-4) = X (Wait, looking at the provided options and the CUCV to YQHA example): C (-4) = Y U (-4) = Q C (-4) = Y V (-4) = R (Wait, the prompt says CUCV to YQHA). Let's re-examine the -4 shift for QIRK: Q (-4) = M I (-4) = E R (-4) = N (or W in some variations, but let's check standard position) K (-4) = G (or P) Based on the options provided (MWEP, MWPE, MEPW, MEWP): Q is the 17th letter. 17 - 4 = 13 (M). I is the 9th letter. 9 - 4 = 5 (E). R is the 18th letter. 18 + 5 = 23 (W) or 18 - 5 = 13. K is the 11th letter. 11 + 5 = 16 (P). The specific pattern applied is -4 for the first two letters and +5 for the last two letters: Q (-4) = M I (-4) = E R (+5) = W K (+5) = P Therefore, QIRK relates to MEWP.
Click below to open Discussion & Feedback
0 Issues
Please login to comment or Report Issues.
Reported Issues
=[AD]=